Land in the Bajo Chaco: 166-km PY12 road 79% done on first section

Paraguay's Ministerio de Obras Públicas y Comunicaciones (MOPC) released on 2 November 2026 the progress report on section 1 of the PY12 road, which crosses the Bajo Chaco in the department of Presidente Hayes starting from Chaco'i. The section runs from km 2.5 to km 37.4 and is 79% complete.

Section 1 in figures

  • Asphalt: 24.86 km of wearing course (carpeta asfáltica) already laid and 30.9 km of granular base.
  • Bridge over the Confuso'i river: 75 metres, 98% complete. Structure and asphalt are finished; the load test and slope protection remain.
  • Bridge over the Negro river: 60 metres, 99% complete. The approach slabs and the load test remain.
  • Access to Nueva Asunción: 2.5 km of rigid pavement, completed.
  • Toll station: civil works 98% complete. Box culverts are finished; a 120-metre paved access to Nanawa is also planned.

The section has been awarded to Consorcio TEC (Tocsa S.A., Ecomipa S.A. and Concret Mix S.A.).

The full corridor: 166 km in four sections

According to an MOPC release of 12 October, the project covers 166 km between Chaco'i and General Bruguez, is financed by the Inter-American Development Bank (IDB) and includes a later maintenance phase. There are four sections:

  • Section 1: km 2.5–37.4, including the access to Nanawa.
  • Section 2: km 37.4–80.2, i.e. 42.8 km (Consorcio Avanza Chaco). By mid-October the structural layers were finished and the polymer-reinforced wearing course was nearing completion.
  • Section 3: km 80.2–122.2, including the access to the Ninfa community (Consorcio Vial Chaco).
  • Section 4: km 122.2–160, plus the access to General Bruguez (Consorcio Chaco Sur).

The ministry's stated aim is a road usable all year round, including in the rainy season, for moving farm output, reaching services and connecting communities with urban centres.

What it means for those investing in Paraguay

  • Reliable access to Bajo Chaco land. A paved road that stays open in the rain changes the time and cost of reaching farms and ranches in the area: it is the first thing to check before assessing a rural property along the corridor.
  • The first stretch is nearly ready. Section 1 starts at Chaco'i and includes the access to Nueva Asunción, already finished.
  • A toll is coming. The toll station's civil works are almost complete; fees and opening date are not given in the release.
  • The title before the road. The value of land depends on its legal standing: cadastre, registry and, in rural colonies, its position with INDERT.

The checks to run on rural land are explained in the articles on land titles and INDERT and on rural colonies; the other roads being paved around the capital in the one on Plan Central 3. The partners.com page on the Real Estate service explains how property is bought in Paraguay.

Sources

Ask our team

A few lines are enough. Our team in Asunción reads every request and replies in your language.

Phone (Optional)

Country code: type the number (with or without +) or the country name, then pick it from the list.

Digits only, without the country code.

If someone from the Partners.com S.A. Introducer Program referred you, enter their 6-character code.

Read More

· By

Real Estate

Property in Paraguay: with 3m accounts frozen, cash buyers lead

Since 3 November 2026 ueno bank's 3 million customers cannot use their accounts or cards, until the exclusion balance sheet that the Banco Central del Paraguay closes within 15 days. Buyers with funds already available at another bank now negotiate with sellers who need certainty on timing.

· By

Real Estate

Buying rural land in Paraguay: only 8% of colony occupants hold title

According to INDERT, on average only 8% of occupants in the 322 colonies created under the 1881 colonisation law have obtained title to their land. With Resolución de Presidencia Nº 2592/2026 the agency places a «Capa de Resguardo» over the colonies and starts a collective regularisation, piloted in two colonies and extended to the rest within 90 days.