Lorries to Brazil: Ciudad del Este freight corridor is 87% built

Two tall pylons of the cable-stayed Integration Bridge under construction over the Paraná river, between green wooded banks.

Paraguay's Ministerio de Obras Públicas y Comunicaciones (MOPC) reported on 28 and 29 October 2026 on the two works that change how the Brazilian border is reached from Ciudad del Este: the Corredor Metropolitano del Este (CMDE), designed for heavy traffic, and the new viaduct at kilometre 10 of the PY02 highway. On 29 October the Government also signed a decree on vehicle weights and dimensions.

The freight corridor: first section 87% built

Rural Lot 1 of the CMDE is 19.1 kilometres of four-lane dual carriageway between Minga Guazú and Cedrales, and it is 87% complete. According to the MOPC, this section is expected to be finished between March and April 2027. The minister, Claudia Centurión, described it as a four-lane motorway with controlled access that reaches the bridge over the Monday river, which in turn links to the Integration Bridge to Foz do Iguaçu.

  • What Lot 1 includes: earthworks, embankments, paving, drainage and a viaduct with a cloverleaf interchange at Cedrales. It is being built by Consorcio CT Vial.
  • The rest of the route: a second rural section and the new bridge over the Monday. The bridge, 500 metres long and 26.5 metres wide, will carry four 3.60-metre lanes, footpaths and cycle lanes; on 7 September 2026 it was 45% physically complete.
  • Works for foreign trade: the programme also includes an urban interconnection, a Zona Primaria for border control and a cargo terminal of the Administración Nacional de Navegación y Puertos (ANNP), intended for import and export operations.
  • Cost and funding: a planned total investment of US$212 million, financed by CAF, the development bank of Latin America and the Caribbean.

The ministry's stated aim is for cargo to reach the border separately from urban traffic, faster and more safely, easing pressure on built-up areas.

The kilometre 10 viaduct

The second site, the Mejoramiento Vial del Nodo Kilómetro 10, is a grade-separated crossing over the PY02, with the service roads on the Monday side, to the south, and the Acaray side, to the north, being upgraded. According to the MOPC, more than 60,000 people pass through it every day, and the minister put the time saved at 20 to 25 minutes per journey. Current work covers service roads, parking, links, ramps, the street beneath the viaduct and a new internal road, plus a cycle lane, footpaths, lighting and box culverts for rainwater. The contractor is Consorcio Acaray-Tocsa and the funding comes from Itaipú Binacional; the ministry gave no completion date.

Vehicle weights and dimensions: rules move to technical regulations

Decree No. 7179 of 29 October 2026, published in Gaceta Oficial No. 289 on 30 October, amends Article 18 of the regulation of Law No. 5016/2014, the Nacional de Tránsito y Seguridad Vial law (Decree No. 3427/2015). The previous text placed large vehicles in category M under three MOPC resolutions from 1997 and 2010. The new point 5.4 states that vehicles and vehicle combinations are subject, as to name, type, outline, axle configuration, weights and dimensions, to the technical regulations set by the competent authority. The decree gives the need to update the rules to new national and regional requirements as its reason; the new limits have not yet been published.

What it means for those doing business in Paraguay

  • A direct route to the bridge from 2027. Shippers sending goods to Brazil from Ciudad del Este will have a four-lane route that avoids the city, if the MOPC's timetable holds.
  • Checks are moving. The Zona Primaria and the ANNP terminal planned in the programme will take part of customs operations out of the centre: worth following before choosing warehouses and depots in the area.
  • Kilometre 10 remains a building site. With no end date, anyone working or delivering along the PY02 should allow for diversions and service roads under construction.
  • Weights and dimensions to check. Lorry fleets should wait for the technical regulations the decree refers to: they will set the limits for axles and loads.

The rules in force from 3 November for crossing the Integration Bridge, including with cargo vehicles, are in the article on the new documents for the bridge to Foz do Iguaçu; the trend in imports from Brazil in the one on imports through September. The partners.com page on the Import-export service explains how trade with Paraguay is organised.

Sources

Ask our team

A few lines are enough. Our team in Asunción reads every request and replies in your language.

Phone (Optional)

Country code: type the number (with or without +) or the country name, then pick it from the list.

Digits only, without the country code.

If someone from the Partners.com S.A. Introducer Program referred you, enter their 6-character code.

Read More

· By

Import / Export

Trade on the Brazilian border: PY17 road paves 221 km in 4 sections

The PY17 road will link Pedro Juan Caballero, Zanja Pytã, Capitán Bado, Itanará and Ypejhú along the Brazilian border with 221 km of paved road, financed by a USD 220 million FONPLATA loan. The first section, 44 km from Pedro Juan Caballero under a PYG 391,554,309,003 contract, is due for completion by February 2028.

· By

Import / Export

Buying goods in Paraguay: dollar at PYG 5,945 and payment upfront

The strong guaraní, with the dollar at PYG 5,945 in October 2026 against PYG 7,105 a year earlier, already cuts the local-currency income of exporters. Since 3 November ueno bank's customers, with the bank in resolution at the Banco Central del Paraguay, also have their accounts frozen: for buyers of goods for export, immediate payment becomes the most valued term.