Homes around Asunción: Plan Central 3 is paving 72.47 km of roads

For anyone buying or renting a home in the Asunción metropolitan area, a paved road outside the plot changes how the property can be used and how long the daily commute takes. Between 29 and 31 October 2026 Paraguay's Ministerio de Obras Públicas y Comunicaciones (MOPC) published the status of three projects in the Central department and neighbouring Nueva Asunción: two lots of Plan Central 3 and the rebuilding of the D027 road.
Plan Central 3: 72.47 kilometres in four cities
According to the note of 31 October, the programme covers 72.47 kilometres of roads in Lambaré, Luque and Itauguá and in parts of Nueva Asunción, in the Presidente Hayes department, serving more than half a million residents. Two lots have published figures:
- Itauguá, lot 2: more than 25 kilometres of roads with asphalt and rigid paving, awarded to Constructora Feldmann S.A. for PYG 38,474,983,828. Work is concentrated on the Cañadita–Valle Karé and Mbói'y–San Juan–Unión Guaraní stretches, where a 4-centimetre layer of asphalt concrete is being laid over the old cobbles.
- Nueva Asunción, lot 5: rehabilitation and paving of Calle 19, the road to Chaco'i, awarded to LT S.A. for PYG 65,601,939,047, with drainage, culverts, gutters and road signs. At the end of October earthworks and culverts were under way, and the sub-base had reached kilometre 3.2.
Alongside Plan Central 3 the ministry lists Plan Central 2, with more than 134 kilometres of paving in Areguá, Capiatá, Guarambaré, Itá, Ñemby and San Lorenzo.
The D027: San Lorenzo–Itá with bus lanes
The D027 links San Lorenzo and Itá and joins the PY01 road. The project covers 26.3 kilometres, half in urban and half in rural sections, under a contract worth PYG 200,897,179,309 including VAT awarded to Consorcio Victoria.
- Bus lanes: from kilometre 0 to 13 the road is being widened with extra lanes for public transport, in rigid paving.
- Works under way: milling of the carriageway at kilometre 13, on one half of the road, and new paving with a hard shoulder between kilometres 13 and 21, near the urban area of Itá.
- Drainage: culverts are still being prefabricated.
What it means if you are buying or renting a home
- Check the stretch, not just the town. The notes name specific stretches (Cañadita–Valle Karé, Mbói'y–San Juan–Unión Guaraní, Calle 19): before an offer, it is worth checking whether the property's road is among those being worked on.
- An open building site. On the D027 work is done on one half of the road: anyone travelling between San Lorenzo and Itá should allow for delays until the works end.
- Public transport. The bus lanes on the first 13 kilometres of the D027 matter to those living along the San Lorenzo–Itá axis without a car.
- Public contracts. Contractors, amounts and lots are published, so progress can be followed.