Trade on the Brazilian border: PY17 road paves 221 km in 4 sections

Red earth road cut through rolling green hills during construction

Paraguay's Ministerio de Obras Públicas y Comunicaciones (MOPC) published on 3 November 2026 the progress report on section 1 of the PY17 road «Niños Mártires de Acosta Ñu», which runs along the Brazilian border in the departments of Amambay and Canindeyú. The section covers the first 44 kilometres from Pedro Juan Caballero.

The project: 221 km in four sections

The works cover 221 kilometres in four sections, including the main alignment, urban crossings (travesías urbanas) and ring roads. Once finished, a paved road will join five border towns:

  • Pedro Juan Caballero, capital of Amambay, where section 1 starts;
  • Zanja Pytã and Capitán Bado, also in Amambay;
  • Itanará and Ypejhú, in Canindeyú.

According to an MOPC release of 15 October, the alignment largely follows the border line, respecting the landmarks that divide the two countries, and is part of national route PY17, which links Pedro Juan Caballero with Salto del Guairá. The project is financed with USD 220 million from the Fondo Financiero para el Desarrollo de la Cuenca del Plata (FONPLATA) under loan contract PAR-27/2019, approved by Law No. 7119/23.

Section 1 in figures

  • Contract: PYG 391,554,309,003, awarded to Consorcio TC (Construpar S.A. and Tecnoedil S.A. Constructora).
  • Deadlines: works due to finish in February 2028, followed by a maintenance period until 2033.
  • Most advanced stretch: between km 19.5 and km 29.5, where the right of way has been cleared, fill placed and the subgrade prepared to carry the pavement layers.
  • Drainage: eight reinforced-concrete box culverts at different points of the route.
  • First stabilised base: between km 15.34 and km 15.78 the cement-stabilised sub-base has been laid.

The picture refers to the September 2026 report. During their supervision mission in October, FONPLATA and the MOPC reviewed the cadastral procedures for all four sections and the quarries supplying aggregates; the environmental licences from the Ministerio del Ambiente y Desarrollo Sostenible (MADES) have been obtained.

What it means for those doing business in Paraguay

  • Northern border logistics change on a known timetable. The ministry names the transport of farm products and other goods as a goal, in a region it describes as highly productive: for anyone buying, storing or selling along the border, February 2028 is the date for the first stretch.
  • Five towns on one road. Once the works are finished, according to the ministry, Pedro Juan Caballero, Zanja Pytã, Capitán Bado, Itanará and Ypejhú will be joined by a paved road: a single axis for border trade.
  • Supplies for the works. Aggregates, cement and reinforced-concrete drainage are needed on all four sections, with a maintenance phase running to 2033.
  • Land along the route. Cadastral procedures for the sections are followed by the ministry and FONPLATA: before assessing a property near the road, it is worth knowing whether the right of way touches it.

The industrial expansions announced to the MIC in Pedro Juan Caballero are covered in the article on October's industrial investments; another road financed by a multilateral bank, in the Chaco, in the one on the PY12 road. The partners.com page on the Import-Export service explains how imports and exports are organised in Paraguay.

Sources

Ask our team

A few lines are enough. Our team in Asunción reads every request and replies in your language.

Phone (Optional)

Country code: type the number (with or without +) or the country name, then pick it from the list.

Digits only, without the country code.

If someone from the Partners.com S.A. Introducer Program referred you, enter their 6-character code.

Read More