Challenging a Paraguay tender result: 7 working days to protest

In Paraguayan public tenders a complaint is called a protesta and is filed with the public procurement authority, the Dirección Nacional de Contrataciones Públicas (DNCP), not with the public body running the tender. The rules are in Law No. 7021/2022, Decree No. 2264/2024 and DNCP Resolution 234/2025; the general framework is in the guide on Law 7021 and the G. 585 million threshold.
What can be challenged
- The tender documents, that is the acts of the call: requirements, criteria, conditions (Law 7021, Art. 127).
- The result, that is the award or the rejection of one's own bid (Art. 127).
Deadlines
- Tender documents: up to the third working day before the opening of bids in a Licitación Pública; up to the second in a Menor Cuantía and in exception procedures announced in advance (Resolution 234/2025, Arts. 58-59).
- Result: within 7 working days of notification (Arts. 58-59).
- Briefing: asking the public body for explanations on the outcome (Decree 2264/2024, Art. 86) does not suspend the deadline to protest (Resolution 234/2025).
How to file
- Through the portal. The protest is filed electronically from the tender's page in the DNCP system, with the «PROTESTAR» action; the DNCP describes the steps in its user guide to legal procedures.
- Content. The filing must contain the minimum set out in Art. 192 of Decree 2264/2024, reproduced in the DNCP regulatory digest.
What happens next
- Admissibility: the DNCP decides whether to admit the protest within 5 working days (Law 7021, Art. 128).
- Suspension: opening the protest suspends the procedure (Art. 129). In any case, the contract is signed only after the protest deadline has passed (Decree 2264/2024, Art. 105).
- Decision: within 35 working days (Art. 129).
- Reconsideration: a DNCP decision can be challenged by a request for reconsideration within 3 working days (Resolution 234/2025, Art. 90; Decree 2264/2024, Art. 220).
- Courts: once the administrative route is exhausted, the case can go to the administrative courts (Law 7021, Art. 156).
What to do beforehand
Clarification questions must be asked within the tender's deadlines: up to the fourth working day before the opening in a Licitación Pública. A condition in the tender documents that seems wrong is challenged before the opening, not after the result. The steps of a tender are in the guide From call to e-bid in Paraguay.
Sources
- DNCP Resolution No. 234/2025 on legal procedures and protests (PDF)
- Dirección Nacional de Contrataciones Públicas, text of Law No. 7021/2022 (PDF)
- Dirección Nacional de Contrataciones Públicas, regulatory digest of Law No. 7021/2022 with Decree No. 2264/2024, January 2026 (PDF)
- Dirección Nacional de Contrataciones Públicas, user guide to procedures (DNCP Res. 234/25)
Ask our team
A few lines are enough. Our team in Asunción reads every request and replies in your language.