Asunción receives 60 building files in the first 19 days of October

The Dirección de Obras Particulares of the Municipality of Asunción, the office that approves building plans in the capital, published on 21 October 2026 a review of its October activity. Between the 1st and the 19th of the month, 60 files entered the system for construction and demolition projects and other building-related procedures; 50 of them were already being registered and reviewed.
Files closed in October
Over the same period the office closed 97 files: 10 new-build projects, 17 plan regularisations, four site-hoarding procedures and 62 final inspections, among other acts. Its director, the architect Nicolás Chaparro, explained that timescales depend on meeting technical, legal and environmental requirements.
Besides multi-storey buildings, the statement notes significant demand for regularising the plans of private homes. Among the areas still drawing investment and new projects, the director names Santa Teresa and Molas López avenues and the Villa Morra district.
The year so far
A municipal statement of 29 April 2026 gives the monthly series of revenue from plan approvals: PYG 4,200 million in January, 5,900 million in February and 9,892 million in March. At the Banco Central del Paraguay reference rate of 21 October 2026, PYG 5,739.08 per dollar, these equal USD 731,825, 1,028,039 and 1,723,621 respectively.
The comparison with the previous year comes from another municipal statement, of 11 March 2025: in January and February 2025 revenue from plan approvals reached PYG 10,758,299,500 (USD 1,874,569), against PYG 4,374,713,860 (USD 762,267) in the same two months of 2024. With 4,200 million in January and 5,900 million in February, the first two months of 2026 stayed below those of 2025; the year's highest figures are those of March and April.
The most frequent errors in submitted plans, according to the head of the Plan Approval Department, the engineer Guido Duarte, concern fire-prevention systems and environmental aspects, particularly effluent management. The Municipality offers a preliminary review with its own technical staff before formal submission.
The construction tax revised in June
In the October statement the director links the interest of large investors to a 15% reduction in construction taxes. The instrument is Ordinance 218/26, passed by the Junta Municipal on 17 June 2026 and signed by the mayor, Luis Bello, which amends the unit prices of the tax set by the general municipal tax ordinance for 2026 (No. 198/25). It stems from a request lodged on 3 December 2025 by the Cámara Paraguaya de Desarrolladores Inmobiliarios, which asked for the tax increase and the measures penalising building height to be suspended. The Dirección de Obras Particulares memorandum of 24 April 2026 quoted in the ordinance recommended «ajustar el alza del impuesto a la construcción al 15%, en lugar del 25% establecido originalmente»: the 15% is therefore the increase that remains, not a discount on the 2025 amount.
In practice, for buildings taller than 13.50 metres the unit price falls from 30.045508 to 27.040957 minimum daily wages (jornales) per square metre, and the separate categories for buildings above 30 and above 100 metres disappear. The other items, from one- and two-storey buildings to demolitions and swimming pools, fall in the same proportion.
Instalments and regularisation
In a statement of 10 August 2026 the office sets out two practical rules. First, applicants may pay the approval fee in instalments, but the approval resolution and the stamping of the plans, which authorise the start of works, are issued only once the last instalment is paid. Second, the SATI digital system accepts new projects but does not yet fully handle regularisation files. Regularisation covers buildings erected without plans, with very old plans or with changes never reported, up to storeys added beyond those authorised, and must be checked against the Plan Regulador.
What it means for those operating in Paraguay
- Works start with the resolution, not the payment. If the approval fee is paid in instalments, works are authorised only after the final instalment and the stamping of the plans: this belongs in the project timetable.
- The tax is calculated in minimum daily wages. Since Ordinance 218/26 the unit price for buildings above 13.50 metres is the same whatever the height: cost estimates should be redone on the table in force.
- Before buying an existing property, compare plans with reality. The Municipality reports buildings with missing or outdated plans, or with more storeys than authorised: whether the building matches its approved plans is a point to check in due diligence.
- Regularisations still have a paper side. SATI covers new projects; regularisation timescales can differ.
- Fire safety and effluents are the most common objections. The preliminary review offered by municipal staff is there to correct them before formal submission.
- The requirements are published. The Municipality provides the sworn declaration and the list of requirements, with a general list for works under 1,000 square metres and under three storeys.
The rules on property brokerage and the upper end of Asunción's rental market were covered in earlier articles, on the brokers' law and on premium rentals.
The partners.com page on the Real Estate service describes how searching for, checking the documents of and buying a property work in Paraguay.
Sources
- Municipality of Asunción, Dirección de Obras Particulares, October 2026 review (21 October 2026)
- Municipality of Asunción, instalments and regularisation (10 August 2026)
- Municipality of Asunción, plan-approval revenue January–April 2026 (29 April 2026)
- Municipality of Asunción, revenue for January and February 2025 and 2024 (11 March 2025)
- Junta Municipal de Asunción, Ordinance 218/26 on construction-tax unit prices (17 June 2026)
- Municipality of Asunción, building forms and requirements
- Banco Central del Paraguay, daily reference exchange rate (sheet of 21 October 2026)