Paraguay's power demand is outrunning the plans: solar, storage and the grid

Paraguay built its energy reputation on a hydropower surplus that seemed inexhaustible. Official figures for 2025 describe a different phase. According to the 2025 National Energy Balance (Balance Energético Nacional) published by the Vice-Ministry of Mines and Energy (VMME), final electricity consumption reached 22,509.5 GWh, up 15.5% in a single year, against average annual growth of 6.9% over 2014-2024. Peak demand on the National Interconnected System (SIN) rose to 5,280 MW, recorded in December, from 5,027 MW in March 2024.
This is the backdrop to the warning from the Paraguayan Institute of Electricity Sector Professionals (IPPSE) which, as reported by ABC Color, flags in a technical report the risk of a power and energy shortfall from 2031.
Who is driving the growth
The main driver is energy-intensive digital activity. Customers in ANDE's high- and medium-voltage Consumo Intensivo Especial categories, which cover data processing, storage, crypto-asset mining, blockchain and data centres, used 5,464.9 GWh in 2025: 2.4 times the 2024 figure, an increase of 138.5%. Measured against final electricity consumption, that is 24.3% of the national total. In its presentation of 18 September 2026, the VMME groups these activities under Advanced Digital Infrastructure (Infraestructura Digital Avanzada).
The effect shows up in exports. In 2025 Paraguay exported 15,539.3 GWh (down 2.9%), while surplus energy ceded to Brazil through Itaipú fell to 10,455.6 GWh (down 19.4%). The official balance attributes the whole contraction to 12.4% growth in energy supplied to the domestic market, partly offset by a 6.7% rise in generation as the Paraná river partially recovered from the extreme hydrological crisis of 2024. Solar remains marginal: 14.6 GWh out of 45,569.1 GWh generated.
What ANDE's master plan proposes
The Generation Master Plan 2024-2043, approved by Resolution P/No. 49741 of 22 October 2024 and updated by Resolution P/No. 50734 of 23 July 2025 to include thermal generation at the VMME's recommendation, assumes demand growth falling from 7.4% at the start of the period to 3.9% at the end, and requires a minimum power reserve margin of 10%. It compares five alternatives, among them:
- Solar and batteries, no new binational dams (option A): 3,729 MW of new capacity by 2033 and 14,069 MW by 2043, at a cost of US$11,321.1 million.
- Solar, batteries and gas turbines (option E): 2,429 MW by 2033 and 12,669 MW by 2043, for US$12,054.9 million.
- New binational dams with Argentina (option C, Itacorá-Itatí and Corpus Christi): 629 MW by 2033 and 4,834 MW by 2043, for US$7,193.8 million. The plan calls for the first four units of each plant in 2034, while noting that binational projects take more than ten years to deliver.
Batteries have a specific role in the document: shaving the midday and evening peaks and optimising the contracting of energy from the binational plants ahead of the review of Annex C of the Itaipú Treaty. The plan also mentions the project to repower Itaipú's 20 turbines from 700 MW to 900 MW each, which would add 2,000 MW for Paraguay and could push back some of the planned works.
The first market step is an international public tender under which ANDE will buy the output of a 140 MWac solar plant at Loma Plata, in the Chaco, to be designed, built and operated by the winning supplier and connected at 220 kV to the existing substation. The public hearing on the draft bidding documents took place on 1 June 2026, according to the hearings register of the National Public Procurement Directorate (Dirección Nacional de Contrataciones Públicas, DNCP). In the hearing documents, ANDE cites Law 7599/2025 on non-conventional, non-hydro renewables, implemented by Decree No. 6034/2026, as the legal framework, and the draft technical specifications set a 27-year supply period. The final bidding documents will be published together with the call for tenders: as of 19 October, the DNCP portal does not yet list it.
The grid constraint
Generating power is not enough; it has to be transported. The Transmission Master Plan 2024-2033 lists 218 projects worth US$3,313.4 million, US$2,702.4 million of it in 2024-2028, and extends the 500 kV network from 835 to 1,875 kilometres. In its second-quarter 2026 accountability report, ANDE puts execution of the 2026 budget allocation at 20% for the 220 kV Villa Hayes–Villa Real–Pozo Colorado–Loma Plata line and at 12% for the 500 kV Yguazú–Valenzuela line.
What it means for investors
- Capacity is now the scarce resource. With digital users at 24.3% of consumption, new high- and medium-voltage connection requests should be assessed against the timetable for new generation, not just the tariff.
- Location matters. Actual availability depends on planned substations and lines; the western Chaco and the 500 kV corridor are the nodes to watch.
- Infrastructure as an opportunity. Option A alone carries US$11,321.1 million of generation spending, and the grid plan another US$3,313.4 million; the new renewables regime and ANDE's tenders will define the room for private capital.
- The 2028-2034 window. The plan's alternatives diverge most in these years, so anyone planning long-lived facilities should track ANDE's decisions year by year.
For guidance on mining and high-density computing projects, see partners.com's Crypto services; for exposure to energy infrastructure, see Safe Investments. This article is for information only and does not constitute legal or financial advice.
Sources
- Vice-Ministry of Mines and Energy, National Energy Balance 2025 (PDF)
- Vice-Ministry of Mines and Energy, National Energy Balance presentation, 18 September 2026
- ANDE, Generation Master Plan 2024-2043 (PDF)
- ANDE, Resolution P/No. 50734 of 23 July 2025 (PDF)
- ANDE, Transmission Master Plan 2024-2033 (PDF)
- ANDE, Accountability Report, second quarter 2026 (PDF)
- National Public Procurement Directorate (DNCP), public hearings register
- ANDE, documents of the public hearing on the Loma Plata solar tender, 1 June 2026 (ZIP)
- Library and Archive of the National Congress, Law No. 7599/2025
- News lead: ABC Color, 18 October 2026