Silvio Pettirossi airport: DINAC puts a new cargo terminal out to tender, with bids due on 26 October

Aerial view of an airport apron where a yellow tug tows a line of five covered cargo dollies.

Paraguay's civil aviation authority, the Dirección Nacional de Aeronáutica Civil (DINAC), has launched a tender to build a new air cargo terminal at Silvio Pettirossi International Airport (AISP) in Luque, the country's main airport. The procedure is National Public Tender No. 43/2026, listed as ID 483745 on the portal of the National Public Procurement Directorate (DNCP), with a reference price of PYG 146,990,376,174. That is USD 25.47 million at the Banco Central del Paraguay reference rate of 16 October 2026 (PYG 5,770.91 per dollar), which is used for every conversion in this article. Published on 24 September, it was still listed as open on 18 October. Bids must be submitted by 08:00 on 26 October 2026 and will be opened in public at 08:30 the same day.

What is being built

The tender specification covers four structures: the cargo terminal itself, an administrative building, a gatehouse and a plant room. DINAC's technical opinion, signed in Luque on 25 August, describes large industrial sheds, steel structures with thermo-acoustic roofing, heavy-duty floors for handling and storing cargo, and specialised electromechanical systems. Part of the site lies in the movement area of the existing apron, inside the airport's Zona Restringida de Seguridad (restricted security zone). The bill of quantities provides for clearing 26,540 square metres of land and 33,233.39 cubic metres of excavation.

For operators, the cold chain is the key element. The price schedule lists three types of cold room: a freezer room at –20 °C with a floor area of 41 m², and chilled rooms of 85 m² and 131 m². Power comes from two transformers rated at 1,000 and 750 kVA and two generator sets of 900 and 780 kVA. The scope also includes video surveillance with image analytics and biometric access control. In its justification for the tender, DINAC's Subdirección de Infraestructura presents the project as a response to growing foreign-trade demand. Its stated aims are to cut handling times between air and road transport and to add capacity for high-value and temperature-sensitive goods.

Timetable and tender terms

Several steps have already passed. The mandatory site visit took place on 7 October and the window for electronic queries closed on 12 October. In Addendum No. 1, dated 13 October, DINAC set the works period at 540 calendar days from the start order. A bidder had pointed out that the specification stated 730 days while the price schedule assumed 18 months. The start order must be issued within ten working days of the contract code being published. A new set of drawings was uploaded to the portal on 16 October, and editable CAD files will go only to the winning bidder.

The tender has a single lot and will be awarded on total price. The financial thresholds are demanding. Bidders need a current ratio of at least 1 and a liabilities-to-assets ratio of no more than 0.80 in their 2023, 2024 and 2025 accounts. They must also show working capital or credit lines equal to 50% of the tender amount (USD 12.74 million), and average annual turnover, over their best five of the last ten years, of at least 70% of the maximum amount (USD 17.83 million). At least one completed contract at an airport terminal is required as well. DINAC turned down two requests to drop that condition, citing the protection of national security, civil aviation and critical infrastructure. It does, however, accept consortia in which only one member brings the airport experience.

The contract includes an advance payment of 20% of the awarded amount (USD 5.09 million if the contract were awarded at the reference price), a 5% bid bond valid for 120 days (USD 1.27 million on the same basis) and a penalty of 0.1% for each day of delay. Prices will be adjusted only if the consumer price index published by the Banco Central del Paraguay moves by 15% or more. Payment is in guaraníes from the 2026 budget, so for a dollar-based contractor the contract's value moves with the exchange rate, a risk the inflation-linked price adjustment does not cover. The 2027 and 2028 instalments depend on budget availability.

The traffic the terminal will handle

According to DINAC statistics, Silvio Pettirossi handled 17,660,665 kilograms of imported and exported cargo between January and August 2026. That is 7.1% more than the 16,483,954 kilograms handled in the same period of 2025. Exports drove the increase, climbing to 2,986,777 kilograms (up 52.8%), while imports reached 14,673,888 kilograms (up 1.0%). The airport handled 957,067 passengers over the same eight months. In August there were 113 international frequencies, 18 fewer than in August 2025, because of flight cancellations. In September DINAC announced, together with LATAM Paraguay, a new direct Asunción–Montevideo route and more frequencies to Lima and São Paulo.

What it means for businesses operating in Paraguay

  • Perishable and sensitive goods. Chilled and frozen storage inside the airport is the development to watch for anyone shipping or receiving temperature-controlled products.
  • Realistic timing. The terminal must still be awarded, contracted and built over 540 days. Until then, air logistics will run through existing facilities, and shipping plans should be built around them.
  • Companies that want to bid. Individuals, companies and consortia listed in the Registro de Proveedores del Estado (State Suppliers Register) may take part. Branches of foreign groups established in Paraguay are eligible, but only the branch's own experience and capacity count.
  • Next milestone. The bid opening on 26 October will show how many bidders came forward, and the outcome will be published on the DNCP portal.

partners.com's Import & Export facilitation page explains how foreign-trade operations in Paraguay are organised. For firms considering a permanent presence in the country, including with an eye on public tenders, partners.com also offers Company Incorporation.

Sources

Ask our team

A few lines are enough. Our team in Asunción reads every request and replies in your language.

Phone (Optional)

Country code: type the number (with or without +) or the country name, then pick it from the list.

Digits only, without the country code.

If someone from the Partners.com S.A. Introducer Program referred you, enter their 6-character code.

Read More

· By

Import / Export

Trade on the Brazilian border: PY17 road paves 221 km in 4 sections

The PY17 road will link Pedro Juan Caballero, Zanja Pytã, Capitán Bado, Itanará and Ypejhú along the Brazilian border with 221 km of paved road, financed by a USD 220 million FONPLATA loan. The first section, 44 km from Pedro Juan Caballero under a PYG 391,554,309,003 contract, is due for completion by February 2028.

· By

Import / Export

Buying goods in Paraguay: dollar at PYG 5,945 and payment upfront

The strong guaraní, with the dollar at PYG 5,945 in October 2026 against PYG 7,105 a year earlier, already cuts the local-currency income of exporters. Since 3 November ueno bank's customers, with the bank in resolution at the Banco Central del Paraguay, also have their accounts frozen: for buyers of goods for export, immediate payment becomes the most valued term.