Powering AI in Paraguay: ANDE's new 220 kV tariff averages US$48.91

When Crusoe and Araico announced their artificial-intelligence computing centre next to the Itaipú substation, neither stated the electricity tariff, as reported in our article of 22 October. The rules now exist. Paraguay's state utility, the Administración Nacional de Electricidad (ANDE), signed Resolución P/N° 52552 on 21 October 2026, creating the Grupo de Consumo de Industrias Electrointensivas de Tecnología Avanzada, and on 23 October announced the first contract signed under that tariff, with the company KUNTUR S.A.
Who is in the new group and who is not
The group covers individuals and companies carrying out artificial intelligence, cloud computing, hyperscale data centre and high-performance computing (HPC) activities. Crypto-asset mining and blockchain transaction validation are excluded: according to the resolution's recitals they stay in the Grupo de Consumo Intensivo Especial set by Resoluciones P/N° 47191/2022 and 49238/2024. Article 2 moves AI, cloud, data centre and HPC users out of that group and into the new one.
Supply is at 220 kV, 66 kV and 23 kV. Among its grounds the resolution cites Decreto N° 6214 of 9 June 2026, whose Article 2 instructs ANDE to adopt measures to attract investment, and Note S. N° 1348 of 21 October 2026 from the Ministry of Industry and Commerce, prepared with the technology ministry (MITIC), which sets the requirements for accrediting projects.
Tariffs by voltage level
- 220 kV: energy at US$0.04110/kWh at peak and 0.03426/kWh off-peak; reserved capacity at US$5.81 and 3.87 per kW a month.
- 66 kV: energy at US$0.04222 and 0.03513/kWh; reserved capacity at US$7.87 and 5.25 per kW a month.
- 23 kV at a station or substation: energy at US$0.04258 and 0.03565/kWh; reserved capacity at US$8.47 and 5.65, capped at 6,000 kW.
- 23 kV on a line: energy at US$0.04554 and 0.03835/kWh; reserved capacity at US$12.32 and 8.22, capped at 2,000 kW.
Compared with Resolución P/N° 49238/2024, which until now also applied to data centres, energy at 220 kV costs 10.3% more in both time bands (from US$0.03725 to 0.04110 at peak, from 0.03105 to 0.03426 off-peak). Users who exceed their reserved capacity pay separately: at 220 kV, US$34.88 per kW a month at peak and 15.49 off-peak.
Tariffs are updated every year by a factor tied half to the US producer price index for industrial commodities and half to US consumer prices, calculated in June and effective from 1 July. The first update comes in 2028 and the factor cannot fall below 1.025, so the minimum rise is 2.5% a year. Every two years tariffs are reviewed against ANDE's average generation cost; if that cost rises by over 30%, the review is a full one. Updated tariffs apply without any contract amendment. The resolution sets no end date for the regime.
The KUNTUR S.A. contract
According to ANDE's statement, the contract runs for 15 years: supply starts on 1 December 2026 at 6 MW and steps up to 286 MW in April 2029. Under the new regime the average tariff works out at US$56.39/MWh at 23 kV and US$48.91/MWh at 220 kV. These are contract averages that combine capacity and energy charges, so they should not be compared with the individual items in the table. Connection works at the Subestación Yguazú are KUNTUR's responsibility, and the company finances the infrastructure in full.
The statement does not say what KUNTUR will do, nor does it link the contract to any other announced project. Crusoe's announcement refers to a facility next to the Itaipú substation; ANDE names the Yguazú substation. The official documents do not show that the two are the same site.
What it means for those investing in Paraguay
- Resolución P/N° 49238 no longer covers data centres. The rules set out in our article on data centre power tariffs remain for crypto-mining; AI, cloud and HPC move to the new group.
- Access depends on a dossier. The annex asks for a sworn declaration of Tier III or TIA-942 Rated 3 certification, projected energy and water efficiency (PUE and WUE), a binding contract with a «de clase mundial» (world-class) client, audited accounts and proof of the lawful origin of funds.
- The land has to be secured first. Title, a long-term lease, a binding option or a reservation before a notary backed by an actual payment are accepted; letters of intent are not.
- The project pays for its connection. The application must state the interconnection substation and the connection CAPEX borne by the user, as in the KUNTUR contract.
- The price rises every year. By at least 2.5% from 2028, plus the two-yearly reviews on generation cost.
The partners.com page on Safe Investments explains how an investment in Paraguay is structured, from checking permits to choosing the vehicle.