·
Data centres in Paraguay: no special tariff, ANDE contracts until 2027

The agreement between Crusoe and Araico for an artificial-intelligence computing centre at Itaipú, covered in an earlier article, does not state the electricity tariff it will be supplied at. This article sets out the framework it fits into: which rules apply today in Paraguay to anyone planning to power a data centre or another high-consumption plant, for how long and who decides.
The 2026 special tariffs are not in force
According to ANDE's statement of 9 June 2026, President Santiago Peña ordered that Decrees 5306 and 5307 of 16 January 2026 and Decrees 5860 and 5861 of 24 April 2026, on so-called industrias convergentes, be left without effect. The statement does not give the number or date of the act through which the repeal was made.
The statement says the decision followed a technical review by the Administración Nacional de Electricidad (ANDE) together with the Ministry of Industry and Commerce, the Ministry of Information and Communication Technologies (MITIC) and the Ministry of Public Works and Communications. The head of the Presidency's Civil Cabinet, Javier Giménez, said the directive allows ANDE to focus on its finances, on carrying out its Plan Maestro and on its cost structure. Industry Minister Marco Riquelme said the aim of attracting industry with Paraguayan energy is unchanged.
The regime in force today: special intensive consumption
For data centres, the rule in force is ANDE's Grupo de Consumo Intensivo Especial. Its basis is Decree 7824 of 16 September 2022, which instructs ANDE to adopt complementary, temporary tariff measures for intensive consumption at extra-high voltage (220 kV), high voltage (66 kV) and medium voltage (23 kV). Article 2 states that these measures must not extend beyond 2027.
Current tariffs are set in ANDE Resolution P/N° 49238 of 26 June 2024 and are expressed in US dollars. At 220 kV, energy costs USD 0.03725/kWh at peak and USD 0.03105/kWh off-peak, that is USD 37.25 and 31.05/MWh; reserved capacity costs USD 5.27/kW per month at peak and 3.51 off-peak. At 66 kV, energy costs USD 0.03765 and 0.03132/kWh, reserved capacity USD 7.02 and 4.68/kW per month.
The Annex to the same resolution defines who belongs to the group: users who consume electricity to process data and provide storage services, including crypto-asset mining, blockchain, tokens and data centres. It also covers any supply with a monthly load factor of 80% or more for two billing cycles, unless a different activity is proven. A Contrato Especial de Suministro with ANDE is required, and its term cannot run beyond 31 December 2027.
The Annex sets a separate route for data centres that do not mine crypto-assets: contract conditions may be reconsidered if the user declares that the centre provides computing services not linked to generating cryptocurrencies or tokens and holds at least an internet-access and data-transmission licence from the Comisión Nacional de Telecomunicaciones (CONATEL). MITIC may carry out the check at ANDE's request.
Electro-intensive industries are a different regime
ANDE's page of tariffs in force also lists Pliego de Tarifas N° 21, the general tariff schedule approved by Decree 6904/2017 and updated to 27 November 2024, and Decree 7551/2017 on Industrias Electrointensivas. The latter covers industries using arc furnaces, electrolysis or similar technologies, or with a monthly load factor of 85% or more, supplied at 220 or 66 kV. It sets invoices in dollars paid in guaraníes, a combined ceiling of 250,000 kilowatts and an annual adjustment linked to US price indices, and states that connection depends on ANDE's technical availability in the area. The text of Decree 7551 does not contain the 2027 deadline, which applies to special intensive consumption.
What it means for those doing business in Paraguay
- The tariffs announced in January and April 2026 are not a basis for calculations. According to ANDE, those four decrees were left without effect; plans built on them need to be redone on the tariffs in force.
- The current reference for a data centre is Resolution P/N° 49238. Dollar tariffs by voltage level and time band, with a mandatory special contract.
- The calendar matters. A special intensive-consumption contract cannot run beyond 31 December 2027: a project with a longer horizon has to account for this.
- After 2027 the framework is open. None of the acts read for this article defines the regime for this type of consumption after 31 December 2027.
- Non-crypto operators have a documentary route. Reconsideration of conditions goes through the CONATEL licence and MITIC's check.
- Capacity is not guaranteed by a tariff schedule. Signing the contract and technical availability remain ANDE decisions.
Power availability in the coming years and ANDE's checks on high-consumption connections were covered in earlier articles on power supply to 2031 and on illegal mining connections in Ciudad del Este.
The partners.com page on the Company service describes how a company is set up and run in Paraguay.
Sources
- ANDE, statement on the repeal of Decrees 5306, 5307, 5860 and 5861 (9 June 2026)
- Decree 7824/2022 on temporary measures for special intensive consumption (16 September 2022)
- ANDE, Resolution P/N° 49238, Grupo de Consumo Intensivo Especial tariffs (26 June 2024)
- ANDE, Annex to Resolution P/N° 49238, general, technical and commercial conditions
- ANDE, tariffs in force
- ANDE, Pliego de Tarifas N° 21, version updated to 27 November 2024
- Decree 7551/2017, tariffs for Industrias Electrointensivas
Ask our team
A few lines are enough. Our team in Asunción reads every request and replies in your language.



