AI data centre next to Itaipú: Crusoe and Araico target 106 MW

The US company Crusoe, which describes itself as an AI factory company, and the Paraguayan energy and infrastructure developer Araico announced in Asunción on 22 October 2026 a strategic partnership to build high-performance AI compute infrastructure powered by the Itaipú hydroelectric dam. According to the press release, it is Crusoe's first dedicated AI Cloud deployment in Latin America, after North America and Europe.
What was announced
Crusoe's release sets three stages. An initial deployment is planned to come online in mid-2027. The project then has a path to scale to 106 MW of IT capacity, meaning the power available to the computing systems. Finally, Crusoe cites long-term options to expand to, in its own words, "approximately 280 MW total".
The facility will sit next to the Itaipú substation and, again according to the company, will tap directly into 100% renewable hydroelectric power. It will serve two groups of customers through Crusoe Cloud: cloud customers in the United States and growing demand within Latin America. For a sense of the source's scale: according to Itaipú, the plant has 20 generating units of 700 MW each, 14,000 MW in total.
Who does what
The split of roles is the most precise part of the release. Araico will lead local development and site infrastructure next to the substation. Crusoe will manage and operate the facility and deliver the physical compute for Crusoe Cloud.
Two different phrasings on the size of the investment
On the economic scale, the two official sources do not use the same words. In Crusoe's release, US Deputy Secretary of State Christopher Landau, who was leading a business delegation in Paraguay when the agreement was signed, says the project "has the potential to be the largest private foreign investment in Paraguayan history". The State Department fact sheet of 21 October 2026 is more cautious: it calls it "potentially one of the largest private investments in Paraguay's history". In both cases this is a potential, not a figure. President Santiago Peña, in the same release, speaks of jobs, investment and technology and of an opportunity for Paraguay to become a regional leader in AI infrastructure.
What was not disclosed
- The amount. Neither Crusoe nor the State Department states how much will be invested.
- Jobs. President Peña and Alejandro Zuccolillo, CEO of Araico, mention them without a number.
- The electricity tariff. Supply terms and the price of power do not appear in the texts.
- The size of the first phase. No capacity is given for the mid-2027 deployment; 106 MW is where the path leads, not where it starts.
- The exact location. The release says "adjacent to the Itaipú substation" without naming the municipality.
- How the two figures relate. The 106 MW is IT capacity; for the "approximately 280 MW total" the release does not explain what is included.
The rest of Landau's visit
The US delegation was in Asunción from 19 to 21 October, with meetings on technology, critical minerals, river infrastructure and logistics. The State Department fact sheet also lists a US$12 million investment by Uranium Energy Corp to develop its uranium concession in Paraguay, the opening in Asunción of an INL office (the State Department's narcotics and law enforcement bureau) as a regional hub for the Southern Cone, and the start of negotiations on a 123 agreement on civil nuclear cooperation.
What it means for those doing business in Paraguay
- The firm date is mid-2027. It is the only timing commitment in the release; later stages are described as a path and as options.
- The power figures should be read for what they are. 106 MW of IT capacity is the target Crusoe states; the "approximately 280 MW" are long-term options.
- The model separates site and operations. A local partner develops the land and infrastructure, the foreign operator runs the compute: this is the structure that anyone assessing energy-intensive facilities in Paraguay finds in this announcement.
- Electricity terms remain unknown. The tariff was not disclosed; no official source states on what terms power will be supplied. The tariff rules currently in force for data centres are explained in a dedicated article.
Growth in electricity demand and ANDE's plan for large digital users were covered in the article on power supply to 2031; the rules on crypto-mining connections in the one on the Ciudad del Este case; foreign capital flows in the one on foreign direct investment in the second quarter of 2026.
The partners.com pages on setting up a local company and on safe investments describe how a company is set up in Paraguay and how an investment in the country is structured.
Sources