Paraguay renewable plants: grid links, transfers and a 51% stake floor

Anyone building or buying a renewable plant connected to Paraguay's grid at 66 kV or more now has written rules for the connection, for the contract with ANDE and for a sale: they are Resolutions No. 1698, 1699 and 1700 of 5 November 2026 of the Ministerio de Obras Públicas y Comunicaciones (MOPC), announced on 11 November and now published on the portal of the Viceministerio de Minas y Energía. The rule that matters most to an investor is in Resolution No. 1700/2026: whoever wins an international tender must remain the majority shareholder of the project company, with at least 51% of the voting capital.
Key points:
- Resolution 1698/2026 sets the technical requirements for connecting solar, wind, biomass and other non-conventional, non-hydro renewable (ERNC) plants to the national grid (SIN) at 66 kV or more.
- Resolution 1699/2026 lists nine mandatory items in connection and supply contracts with ANDE or the local distribution concessionaire.
- Resolution 1700/2026 governs transfers of contracts, surplus-energy credits and shares: a 51% minimum for the tender winner and 90 days for the buyer to obtain the environmental licence in its own name.
What the three resolutions establish
The three resolutions, signed by the minister on 5 November 2026, implement Law No. 7599/2025 on non-conventional, non-hydro renewable energy and its regulation, Decree No. 6034/2026. The MOPC presented them in a note dated 11 November; the texts are signed scans.
- Resolution No. 1698/2026, the connection: it approves four annexes (technical connection and power-quality requirements, operating protocol, testing and technical commissioning, metering system) that are mandatory for every plant connected at 66,000 volts or more, whatever the technology. Connection is authorised within the contract with ANDE or the concessionaire. ANDE may add specific requirements in tenders and contracts, never less demanding than the annexes.
- Resolution No. 1699/2026, the contract: every connection and supply contract at 66 kV or more must cover the connection point, the relationship with ANDE's dispatch centre, tests and certifications, metering, basic commercial terms, reporting duties, grounds for suspension and termination, the transfer regime and dispute resolution. For self-generators and cogenerators the law allows contracts of up to 30 years (Articles 16 and 22 of Law No. 7599/2025, cited in the resolution).
- Resolution No. 1700/2026, transfers: contracts, credits for energy fed into the grid and shares in the project company can be transferred, but only on the written conditions set out below.
A plant's stages under Resolution 1698
- Construction: the generator submits the technical studies in Annex I with the detailed design, approved by ANDE where required, and passes the Annex III tests. A positive result leads to the plant's Acta de Habilitación Técnica (technical commissioning certificate).
- Operation and maintenance: the plant feeds energy into the grid according to the contract schedule and its own operating protocol, under ANDE's or the concessionaire's continuous oversight, with periodic tests.
- Changes: the Annex I requirements on electrical disturbances can only be changed by a new MOPC resolution, after consulting ANDE.
Selling a plant: what Resolution 1700 requires
A full or partial transfer is possible only once the plant has started supplying energy. Requirements depend on the type of holder:
- ERNC generator or exporter: the buyer must be a legal entity with the technical capacity and financial standing to operate and maintain the plant. It files with the MOPC its articles of incorporation registered with the Registros Públicos, the signatory's powers, a list of directors, installed capacity in MW, the plant's coordinates, proof of financial capacity and the letter of intent for the transfer. The buyer sets up a domicile in Paraguay; a foreign company must also appoint a resident legal representative.
- ERNC self-generator or cogenerator: the buyer must first hold its own ERNC licence.
- Plants up to 1 MW: the buyer only needs to be listed in the MOPC's ERNC Registry.
- After ANDE's approval: the buyer has 90 calendar days to file with the MOPC an environmental licence in its own name, or the ERNC licence can be cancelled after an administrative procedure.
- Surplus credits: a self-generator can transfer to third parties its credits for energy fed into the grid by notarial deed (escritura pública) notified to ANDE or the concessionaire, which credits them to the buyer from the next billing cycle.
The project company and the 51% rule
For ERNC generators awarded through an international public tender, the plant sits in a Sociedad de Objeto Específico (SOE, special-purpose company). Resolution 1700 sets three limits:
- the tender winner remains the majority shareholder with at least 51% of the voting capital, or the higher share set in the tender documents;
- companies that bid in the same tender without winning cannot become shareholders;
- any new third-party shareholder needs ANDE's prior, reasoned authorisation, and if the winner is a consortium any change in its shares also needs a favourable opinion from the MOPC.
Transferring without approval or changing control of the SOE is a serious offence under Law No. 7599/2025, which can lead to forfeiture of the ERNC licence or termination of the contract.
Which route applies to which plant
- Up to 1 MW, for own use: listing in the ERNC Registry, no licence; a buyer of the plant must also be listed.
- Self-generator or cogenerator above 1 MW: ERNC licence; contract with ANDE of up to 30 years; the incoming owner needs its licence before the transfer.
- Connection at 66 kV or more: the four annexes of Resolution 1698 apply to everyone, from self-generators to exporters.
- Generator awarded through an international tender: SOE with at least 51% held by the winner; a financial partner can come in as a minority shareholder, within the tender's maximum share and with ANDE's authorisation.
What it means for investors in Paraguay
- Control cannot be sold outright. In a project won through an international tender, a later investor can buy a minority stake at most.
- Exit is possible, but after commissioning. Contracts and shares can be transferred only once the plant supplies energy.
- Buyers face a deadline. Ninety days to obtain the environmental licence in their own name after ANDE's approval.
- Surplus credits are a transferable asset. They are assigned by notarial deed and show up on the bill from the next cycle.
The registry for plants up to 1 MW is covered in the article on running your own renewable plant; medium-term power supply in the one on electricity to 2031. Partners.com's Company Formation page explains how to set up a business in Paraguay.
Sources
- Ministerio de Obras Públicas y Comunicaciones, three new renewable-energy resolutions (11 November 2026)
- MOPC Resolution No. 1698/2026, guidelines for grid-connection authorisation at 66 kV or more (5 November 2026)
- MOPC Resolution No. 1699/2026, guidelines for connection and supply contracts with ANDE (5 November 2026)
- MOPC Resolution No. 1700/2026, transfer regime for contracts, credits and SOE shares (5 November 2026)